GEORGE TOWN, September 20 – A pipe diversion works need to be carried out and requires shutting down of the existing 750mm MS and 450mm CI main pipeline along Jalan Air Itam and Jalan Scotland. This is to facilitate the connection works at Jalan Masjid Negeri/Jalan Scotland, Daerah Timur Laut, Penang on Saturday, 25.9.2021. There are four (4) connections involving the existing 750mm MS and 450mm CI pipe along Jalan Air Itam and Jalan Scotland.
| Time/Day/Date | 9.00am – 11.00pm, Saturday, 25 September 2021. |
| Reason
|
Shutting down of 750mm Mild Steel (MS) and 450mm Cast Iron (CI) Main Pipeline for pipe diversion works at Jalan Masjid Negeri / Jalan Scotland Flyover, DTL, Penang. |
| No. of water accounts affected | 200. |
This pipeline shutdown will cause a 14-hour scheduled water supply interruption in certain areas at Jalan Scotland. About 200 water accounts will be affected by this water supply interruption. Consumers in the following areas are hereby advised to store sufficient water for use for 14 hours, from 9.00am to 11.00pm on Saturday, 25 September 2021:
| 1. | Jalan Scotland | 6. | Wisma Yatim Perempuan Islam Pulau Pinang |
| 2. | Scots Pavilion | 7. | SMK Agama Al Mashoor |
| 3. | Children Protection Society | 8. | Seri Cahaya Condo (Kampung Baru) |
| 4. | Scotland Park | 9. | Solok Scotland |
| 5. | Asrama Ramakrishna |
PBAPP deeply regrets for the temporary inconvenience caused. Please store sufficient water for use during the interruption.