Summary
  • Package 1 of the Juru-Sungai Dua Elevated Highway project has reached 40.79% completion.
  • Package 1 is expected to be completed by October 2027.
  • Tenders for Packages 2 to 5 are targeted for completion by end-2026, with work expected to begin in early 2027.
  • The RM3 billion project is expected to benefit about 200,000 road users daily and be fully completed by end-2030.

SEBERANG JAYA, September 8 — Package 1 of the RM3 billion Juru-Sungai Dua Elevated Highway project has reached 40.79% completion and is targeted for completion by October 2027.

Chief Minister Chow Kon Yeow said on Monday. Packages 2 to 5 are undergoing tender evaluation, with construction expected to begin in early 2027.

Chow said land acquisition and utility relocation would proceed concurrently to minimise delays. The project, targeted for full completion by end-2030.

Is expected to benefit about 200,000 road users daily by separating local and highway traffic along the heavily congested corridor. Only seven food stalls are expected to be affected, with no major relocation required.