Summary
  • A long-term lane diversion begins Sept 12 in Bayan Lepas.
  • It affects Jalan Sultan Azlan Shah towards Teluk Kumbar.
  • The diversion will remain until July 31, 2027.
  • Works involve bored piling and permanent structures for the Mutiara Line.

BAYAN LEPAS, September 10 — A long-term lane diversion will be implemented along Jalan Sultan Azlan Shah towards Teluk Kumbar from Sept 12 until July 31, 2027.

For Penang Mutiara Line construction. The affected stretch runs from near Acre Works’ construction area to the junction at Penang Airport Taxi Limousine Services.

The diversion will facilitate bored piling and permanent structure works within the road median under the LRT project’s CMC1 package. Motorists are advised to follow traffic signs and exercise caution.

Safety barriers, cones and flagmen will be deployed, while the project’s emergency response team will assist with traffic management.