Summary
  • Installation of parapets and median concrete barriers along the elevated highway in Farlim has been completed.
  • Seven major construction works remain outstanding, including street lighting, drainage and road surfacing.
  • Wong Hon Wai urges contractors and relevant agencies to resolve traffic, road conditions and water overflow issues.

GEORGE TOWN, November 26ย โ€” The new highway connecting Thean Teik in Farlim to the Tun Dr Lim Chong Eu Expressway has recorded further construction progress.

With all parapets and median concrete safety barriers on the elevated section in Farlim completed. Penang executive councillor Wong Hon Wai said he recently attended a coordination meeting.

To review construction progress and address outstanding issues. Remaining works include street lighting installation, below-deck median drainage, rainwater downpipes.

Below-deck median barriers, road signage, asphalt surfacing and expansion joints. Wong also raised concerns regarding traffic management, construction site cleanliness, road conditions and rainwater overflow.

He stressed that the contractors and relevant agencies must resolve all outstanding issues to ensure the remaining construction works progress smoothly.